Addition of Canopy to the vehicle number-DHAKA-METRO-THA-13-4850 of Chittagong Training Centre, BPDB, Chattogram.
WRK3/e-GP/20260730/1285794/00258687
|
Chittagong Training Centre |
৳২.৯৯ লাখ |
৭ জুন ২০২৬ |
Completed |
|
Repair and maintenance work of vehicle no. CHATTA-METRO-GHA-05-0062 of Chittagong Training Centre, BPDB, Chattagram.
WRK1/e-GP/20260730/1277836/00258686
|
Chittagong Training Centre |
৳৯৯,৪৫০ |
১৭ মে ২০২৬ |
Completed |
|
Repair and maintenance work of vehicle no.-Dhaka-Metro-THA-13-4850 of Chittagong Training Centre, BPDB, Chattogram.
WRK2/e-GP/20260730/1232167/00258685
|
Chittagong Training Centre |
৳৯৯,৯০০ |
১৯ ফেব ২০২৬ |
Completed |
|
Procurement of paper, notebooks, pens, file folders, certificates, etc. and other materials for the trainees of the training in Chittagong Training Centre, BPDB, Chattogram.
GRS5/e-GP/20260730/1163881/00258683
|
Chittagong Training Centre |
৳৯৯,৮৮৮ |
২৬ অক্টো ২০২৫ |
Completed |
|
Procurement of various printing and stationery items including note sheets, paper, notebooks, pens, etc. for office work, and computer accessories used for office work, and all items including photocopier and computer printer cartridges/ribbons, etc. for Chittagong Training Centre, BPDB, Chattogram.
GRS1/e-GP/20260730/1162387/00258684
|
Chittagong Training Centre |
৳৯৯,৭৪৫ |
২৩ অক্টো ২০২৫ |
Completed |
|
Repair & maintenance of Office Building including Passage, Stairs,Toilet,Thai-grill, wooden door & key, lighting , Blinder and water supply system under S & D Division- Hatahazari, BPDB, Ctg.
C-2 22-23/e-GP/20231105/790570/00122195
|
Office of the Executive Engineer, S&D Division-Hathazari,Chittagong |
৳৩.৯৯ লাখ |
১৬ ফেব ২০২৩ |
Completed |
|
Repair & maintenance of One storied building (Officer's Residence Part) including Passage, Stairs, Floor Tiles, Thai-grill, wooden door & key, floor mosaic cleaning, lighting and water supply system under S & D Division- Hatahazari, BPDB, Ctg.
C-1 22-23/e-GP/20231105/755564/00122187
|
Office of the Executive Engineer, S&D Division-Hathazari,Chittagong |
৳৫.০০ লাখ |
২৭ নভে ২০২২ |
Completed |
|
Repair & maintenance of One storied building (Anser Residance Part) including Floor Tiles, Thai-grill, wooden door & key, Toilet, floor mosaic cleaning, lighting and water supply Cleaning, lighting & external Works Under S&D Division- Hatahazari, BPDB , Ctg.
C-3 22-23/e-GP/20231105/755585/00122191
|
Office of the Executive Engineer, S&D Division-Hathazari,Chittagong |
৳৩.০০ লাখ |
২৭ নভে ২০২২ |
Completed |
|
Maintenance of Power Transformer 1 & 2, Coloring, Earthing 33/11 Substation new Installation GIS Bus to Change Silica gel & Brider Box 33/11 kv switch yard under S&D Division-Barabkunda, BPDB, Ctg.
WR-10../e-GP/20220826/636459/0031579
|
Sales & Distribution Division, barabkunda, Chittagong |
৳৪.৯৯ লাখ |
৬ ফেব ২০২২ |
Completed |
|
Repair & maintenance of drainage system & external Work At Hathazari SS Under S&D Division- Hatahazari, BPDB , Ctg.
HAT-C4/e-GP/20220825/644628/0031471
|
Office of the Executive Engineer, S&D Division-Hathazari,Chittagong |
৳৩.০০ লাখ |
১০ জানু ২০২২ |
Completed |
|
Supply and Installation AC at 33/11 KV Hathazari SS & 33/11 KV Foteyabad SS under S&D Divn.- Hathazari, BPDB, Ctg.
HAT-MM-1/e-GP/20220825/644634/0031473
|
Office of the Executive Engineer, S&D Division-Hathazari,Chittagong |
৳৯.০০ লাখ |
১০ জানু ২০২২ |
Completed |
|
Repair & maintenance of drainage system Cleaning, lighting & external Work At 33/11KV Foteyabad SS Under S&D Division- Hatahazari, BPDB , Ctg.
HAT-C3/e-GP/20220825/644631/0031470
|
Office of the Executive Engineer, S&D Division-Hathazari,Chittagong |
৳৩.০০ লাখ |
১০ জানু ২০২২ |
Completed |
|
Right off way of 33 KV Hathazari Ckt-01 , 02 Feeder & 11KV H-01,H-02, H-04, H-05 Feeder at 33/11KV Kolabagan SS and 33 KV Foteyabad Ckt Feeder & 11KV F-01,F-02, F-03, F-04, F-05, F-06 Feeder at 33/11KV Foteyabad SS under S&D Division- Hathazari, BBPDB,Ctg.
HAT-WR-7/e-GP/20220825/644609/0031469
|
Office of the Executive Engineer, S&D Division-Hathazari,Chittagong |
৳৪.৯৯ লাখ |
১০ জানু ২০২২ |
Completed |
|
Work of 1 phase transformer installation,.4 kv line rescue and related to reduce system loss due to hooking work in 11kv feeder kalurghat-14 spreading over ekota colony, sahaji bari majar,mokbul contractor bari under S&D kalurghat,BPDB ,Ctg.
BW03/e-GP/20231105/627164/00122302
|
Office of the Executive Engineer,Sales & Distribution Division Kalurghat, Chittagong |
৳১১.৩৭ লাখ |
২৮ নভে ২০২১ |
Completed |
|
Work of 1 phase transformer installation,.4 kv line rescue and related to reduce system loss due to hooking work in 11kv feeder kalurghat-02 spreading over ekota colony, sahaji bari majar,mokbul contractor bari under s&d kalurghat,BPDB,Ctg.
PR004/e-GP/20231105/627168/00122301
|
Office of the Executive Engineer,Sales & Distribution Division Kalurghat, Chittagong |
৳৭.৯৪ লাখ |
২৫ নভে ২০২১ |
Completed |
|
Rescuing threading structure in sabaghata hamidchor area and change them with PC pole changing eye connector and heat sink kit in both side of rattarpole Flyover erecting of Isolator at Bakolia grid side and Tree Trimming repair and maintenance work of 33KV Bakolia-Kalurghat CKT Spreading over hamidchor ilias brothers house One KM under sales and distribution division kalurghat.
LM31/e-GP/20220705/563983/0025765
|
Office of the Executive Engineer,Sales & Distribution Division Kalurghat, Chittagong |
৳৭.০০ লাখ |
১১ এপ্রিল ২০২১ |
Completed |
|
Maintenance Buckloz Relay Change Brither Box with Silica gel Oil Centrifusing Works of Power Transformer 1& 2 and earthing installation of Substation of 33/11 kv switch yard under S&D Division-Barabkunda BPDB Ctg.
WR- 11./e-GP/20220826/506936/0031574
|
Sales & Distribution Division, barabkunda, Chittagong |
৳৩.৯৯ লাখ |
২৯ অক্টো ২০২০ |
Completed |
|
Renovation & maintenance works of Baroawlia-Barabkunda 33 KV Ckt-2 to Jumper change Wire Re-tensioning and old wires change under Sales & Distribution Division-Barabkunda BPDB Chittagong.
WR-06./e-GP/20220826/504020/0031575
|
Sales & Distribution Division, barabkunda, Chittagong |
৳৪.৯৯ লাখ |
১৫ অক্টো ২০২০ |
Completed |
|
Construction of new feeder with installation of feeder cable and related development works dividing 11 kv feeder no.02 due to Overload removal removing low voltage problem and reducing system loss said feeders under Sales & Distribution Division-Barabkunda BPDB Ctg.
SWR-3./e-GP/20220826/503912/0031577
|
Sales & Distribution Division, barabkunda, Chittagong |
৳৫.৯৭ লাখ |
১৫ অক্টো ২০২০ |
Completed |
|
Construction of new feeder with installation of feeder cable and related development works dividing 11 kv feeder no.04 due to Overload removal removing low voltage problem and reducing system loss said feeders under Sales & Distribution Division-Barabkunda BPDB Ctg.
SWR-2./e-GP/20220826/502629/0031578
|
Sales & Distribution Division, barabkunda, Chittagong |
৳৬.৯৯ লাখ |
১২ অক্টো ২০২০ |
Completed |
|
Renovation & maintenance works of 33 KV Chemical Feeder to Jumper change Wire Re-tensioning and old wires change under Sales & Distribution Division-Barabkunda BPDB Chittagong.
WR-07./e-GP/20220826/502622/0031576
|
Sales & Distribution Division, barabkunda, Chittagong |
৳৪.৯৮ লাখ |
১২ অক্টো ২০২০ |
Completed |
|
Renovation & maintenance works of Baro-aulia BF/02 BF/04BF/1411KV feeder including installation of single phase/3 phase distribution X-formerSystem Development and removal of 0.4KV lines to reduce system loss due to hooking at different location of said feeders as well as related works Remove & Replace of 11/0.4KV different rating 3-phase distribution X-former under S&D Division-Fouzderhat PDB Chittagong.
LW28/e-GP/20220826/381305/0031581
|
Sales and Distribution Division, Fouzderhat, BPDB, Chittagong |
৳৬.০০ লাখ |
১৭ নভে ২০১৯ |
Completed |
|
HPW-87Renovation work of 11KV 11/0.4KV line under Development of Power Distribution System In Three Hilly Districts Bandarban at Thanchi Alikadam Naikkayngchari Upazilla Various area and adjacent area under Bandarban District.
HPW-87/e-GP/20220831/334857/0032747
|
Development of Power Distribution System in Three Hilly Dristricts. |
৳৪৬.৪৬ লাখ |
৬ আগ ২০১৯ |
Completed |
|
Construction of new 11KV 11/0.4KV line under Development of Power Distribution System In Three Hilly Districts at Kawkhali Upazilla Bagkhaiya Gona to Dabua Chowduri Para Balukhali Pochu Para Bazer Dhupchari Headman Para Dabua Bazer and adjacent area.
HPW-58/e-GP/20220831/321089/0032744
|
Development of Power Distribution System in Three Hilly Dristricts. |
৳২১.৭০ লাখ |
২৭ মে ২০১৯ |
Completed |
|
Repairing and maintenance work of Ground floor & 1st floor coridor with Wall cabinet warring spotlight and other necessary interior design works at Executive Engineer office room & officers room under S & D Kalurghat BPDB Chittagong
CMW-7-18-19/e-GP/20220705/321627/0025763
|
Office of the Executive Engineer,Sales & Distribution Division Kalurghat, Chittagong |
৳৪.৯৮ লাখ |
২৭ মে ২০১৯ |
Completed |
|
Construction of new 11KV 11/0.4KV line under Development of Power Distribution System In Three Hilly Districts at Kawkhali Upazilla Chaikrorui Bazer to Bagkhaiya Gona 1No Hatimara Rawjan Gona Mohajon Para and adjacent area.
HPW-57/e-GP/20220831/321087/0032741
|
Development of Power Distribution System in Three Hilly Dristricts. |
৳২৪.৬৭ লাখ |
২৭ মে ২০১৯ |
Completed |
|
Construction of new 11KV 11/0.4KV line under Development of Power Distribution System In Three Hilly Districts at Lama Upazilla Gojalia Union Sapmara to Gojalia and adjacent area.
HPW-67/e-GP/20220831/304790/0032738
|
Development of Power Distribution System in Three Hilly Dristricts. |
৳৩৭.৭০ লাখ |
১০ এপ্রিল ২০১৯ |
Completed |
|
Construction of New 33KV Line Merlin from Manikchari S/S to Laxmichari S/S.
HPW-005/e-GP/20220831/237267/0032734
|
Development of Power Distribution System in Three Hilly Dristricts. |
৳৮২.৯৬ লাখ |
২৩ অক্টো ২০১৮ |
Completed |
|
Supplying for Everyday used DCS Meter Reading Book Computer Lger Sheet Disconnect and reconnect form Jamatat Bill Form and other printing at Sales and Distribution BPDB Kalurghat.
S..04/e-GP/20220705/203302/0025762
|
Office of the Executive Engineer,Sales & Distribution Division Kalurghat, Chittagong |
৳২.০০ লাখ |
৩১ মে ২০১৮ |
Completed |
|
Supplying for Everyday used Different From and Registrar at Sales and Distribution BPDB Kalurghat.
S..05/e-GP/20220705/203304/0025760
|
Office of the Executive Engineer,Sales & Distribution Division Kalurghat, Chittagong |
৳২.০০ লাখ |
৩১ মে ২০১৮ |
Completed |
|
Repair & Maintenance works of Bakulia-Muradpur 33Kv Line under BBB-Kalurghat BPDB Chittagong.
SL.06/e-GP/20220705/127960/0025755
|
Office of the Executive Engineer,Sales & Distribution Division Kalurghat, Chittagong |
৳৩.০০ লাখ |
২৫ অক্টো ২০১৭ |
Completed |
|
Establishment / Replacement of Load Transfer Transformer & Transformer Earithing L.T Side Fabricatated Gang Fuse Carrier Installation 11Kv Kalurghat-15 No Feeder under Sales and Distribution Kalurghat BPDB Chittagong.
SL.12/e-GP/20220705/127944/0025753
|
Office of the Executive Engineer,Sales & Distribution Division Kalurghat, Chittagong |
৳৪.০০ লাখ |
২৫ অক্টো ২০১৭ |
Completed |
|
Repair & Maintenance works of Bakulia-Kalurghat 33Kv Line under BBB-Kalurghat BPDB Chittagong.
SL.05/e-GP/20220705/126062/0025756
|
Office of the Executive Engineer,Sales & Distribution Division Kalurghat, Chittagong |
৳২.৯৯ লাখ |
২৫ অক্টো ২০১৭ |
Completed |
|
Repair & Maintenance works of Kalurghat 33/11 Kv Sub-station under BBB-Kalurghat BPDB Chittagong.
SL.03/e-GP/20220624/126162/0012883
|
Office of the Executive Engineer,Sales & Distribution Division Kalurghat, Chittagong |
৳৩.০০ লাখ |
১৬ অক্টো ২০১৭ |
Completed |
|
New Transformer Installation for load sharing repair and maintenance of 11/0.4 KV Line Maintenance and method development of 0.4 KV line Opening and re-fixing of Bundled cables at Golam Ali Nazir Bari Nath Para Kala Mia school Jele para Nuruzzaman Nazir Bari Nurul Islam B.Sc. Bari Nurul Islam Sodagor bari Moulavi pukur par area etc under 11 KV feeder no Kalurghat-10 of Sales and Distribution Kalurghat BPDB Chittagong.
SL.11/e-GP/20220705/126065/0025751
|
Office of the Executive Engineer,Sales & Distribution Division Kalurghat, Chittagong |
৳৪.০০ লাখ |
১৬ অক্টো ২০১৭ |
Completed |
|
Repair & Maintenance works of Muradpur 33/11 Kv Sub-station under BBB-Kalurghat BPDB Chittagong.
SL.04/e-GP/20220705/126060/0025752
|
Office of the Executive Engineer,Sales & Distribution Division Kalurghat, Chittagong |
৳২.৯৯ লাখ |
১৬ অক্টো ২০১৭ |
Completed |
|
Urgent Operation and maintainence work 11 kv line, 11/0.4kv line, 0.4kv line & 250KVA 11/0.4kv transformers installation & load sharing, maintainence and renovation work in 11kv feeder-13 area around Ashraf Ali Road, Bacha Mia Road, Sorai Para etc. as per schedule of s&d-pahatoli, BPDB, Chittagong.
EGP(2016-2017)-O&M(R)-W-23/e-GP/20220624/103873/0012723
|
Sales & Distribution Divisiton-Pahartali, BPDB, Ctg. |
৳১.৯৯ লাখ |
২২ মে ২০১৭ |
Completed |