Typical rates
At what % of the estimate jobs are won
What share of the official estimate jobs are really won at, by type of work. Worked out from the last 3 years of e-GP records, only for jobs where the estimate (APP) could be matched.
Only this office: Chief Chemist, Bibiyana South 400 MW Combined Cycle Power Plant, BPDB, Parkul, Nabiganj, Habiganj.. See all offices
Chief Chemist, Bibiyana South 400 MW Combined Cycle Power Plant, BPDB, Parkul, Nabiganj, Habiganj.
| Nature | Typical | Middle range | Jobs counted |
|---|---|---|---|
| All types together | 74% | 61% to 89% | 22 |
| Works | 88% | 88% to 89% | 5 |
| Goods | 65% | 61% to 88% | 17 |
For example, 90% means a job with a 1 crore estimate was won at 90 lakh.
This is worked out from public e-GP records and is not a guarantee. Before you bid, check the tender's own estimate and the type of work. Groups with fewer than 5 jobs are not shown.
Want the full competitor list and your price range? See it in the Bid Brief →